  • Project's Title Site Development for Khurais Central Processing Facilities Project
  • Client ARAMCO & HYUNDAI ENGINEERING
  • Consultant SAUDI ARAMCO
  • Value of the Project 43,000,000.00 SR
  • Time Frame 15th January 2007 till 21st November 2007
  • Location of Project Khurais, K.S.A.
  • Highlights Site Development

Khurais Central Gas Processing Facilities

Entire Site Development of "Khurais Central Gas Processing Facilities" SAUDI ARAMCO project, HYUNDAI ENGINEERING as main contractor to build Gas processing trains, ETE's job includes complete site development and related works.

Key Features of the Project

  • Site preparation of 300,000 m2
  • Backfilling of 356,000 m3
  • 78,000 m3 of base course laid over the select fill material
  • Asphalting works, external utilities etc